MGMT6056 Contemporary Leadership Strategies
0 Download9 Pages / 2,126 Words
Course Code: MGMT6056
University: Johnson And Wales University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: United States
Question:
Each student/group can evaluate these items and decide which ones they want to take action on. You don’t have to address all of these, but these issues were addressed in the best project submissions. Many of these items you may have already have planned to incorporate into your project. These items are listed in random order:
Ensure you comply with the assignment instructions, including metrics such as durations and number of WP’s and Activities, etc.
Review all of your feedback to date, for all of your assignments in both Time and Cost.
In order to clearly demonstrate that you have a complete WBS in your project you need a total project deliverable that sums up the entire project, and then possibly some sub-deliverables, then definitely Work Packages with at least 1 Activity beneath each WP.
You should have a WBS code visible either through a WBS column, or via the use of Outline Number. Either way, the highest level Deliverable, your overall Project, should start with a Code of 1. This code should be used consistently across your Excel, Word and .mpp files.
When you transfer your WBS over to MS Project, ensure your MS Project hierarchy (indents) don’t show a WP beneath another WP in the hierarchy.
Make sure your Chart in your Excel Costing Sheet is set to use the right input cells, as you change your columns, you may end up with the incorrect range of input cells to the chart.
Ensure your cells for your WBS Costs in your Time Phase Budget worksheet, in your Excel Costing Sheet, use formulas (see Excel Costing Sheet Example) that link back to the individual WBS worksheets.
Make sure your labour and material costs in your Excel Costing Sheet align with your .mpp file. Start by looking at the total project cost in each. Your Excel Costing Sheet may be a bit higher because it may have Activity Contingencies and sometimes a Management Reserve, depending on which cells you are looking at.
Insert the column “Work” in your Gantt chart. If your Excel Costing Sheet indicated Activity C needs 12 hours of labour, then you should see 12 hours of work in your .mpp file for that Activity.
Ensure you are using predecessor and successor relationships only between Activities, and not Summary Tasks in MS Project (WP’s or higher level sub-deliverables in your WBS).
Ensure you check all your Activities for necessary predecessors. If you don’t have a predecessor for an Activity, that means you are saying there is nothing stopping that Activity from being done immediately.
Ensure you Baseline your project, before you Status your project (add a % Work Complete), and definitely Baseline before you use MS Project Options to change how “Actual costs are always calculated by Project”.
Answer:
Introduction
This report depicts the design and development of Supply Chain Management System in the business organization that helps to provide more interactive opportunities to the suppliers, consumes and distributors as well. The Module of Enterprise Resource Planning system that has been chosen is Supply Chain Management (SCM).
In order to develop the SCM system the activities those have been selected to take effective decision making are considered in this assignment. A Strategic Management Plan, Activity on Node (AON), WBS, Activity duration tables are all elaborated in this assignment. In addition to this, a Gantt chart and a resource management program are elaborated in this assignment.
Strategic management plan
In this new era of technology mostly for managing information, material details, raw material and cash flow Supply Chain management (SCM) is widely used in both the medium and large sized enterprises. SMC is an implementation action or integrative business philosophy used for managing mainly materials. In other words SCM helps to reduce operational cost and delay distribution by improving the supply flow to satisfy global consumers. The current globalization scenario shows that, SCM and customer service has become a significant aspect in corporate world. The SCM will give direct interacting opportunities to the consumers, distributors and suppliers.
Schedule Module development
AON (Activity on Node) diagram.
Figure 1: Activity on Nodes for the SCM implementation project
(Source: Created by author)
Project schedule model maintenance
Frequency
By who
Monthly
System developer, project manager
Control thresholds
Project level
When
Units
Variance measured
Management level
Execution phase
Rule of performance measured
Frequency
By who
Rule of EVM measured
Weekly
Finance manager
Reporting format
Report content
To whom
Done by whom
Frequency
Progress status
Project objectives
Goals
Project manager
Team workers
Monthly
Work breakdown structure
WBS
Task Name
0
Developing project schedule for SCM
1
Project design phase
1.1
Implementation of project team
1.1.1
performance analysis
1.1.2
Worker’s skill measurement
1.2
communication management program
1.2.1
Inventory management plan
1.2.2
Team meeting
1.3
Resource identification
1.3.1
Gathering
1.3.2
Analysis
1.4
Identification of supply chain characteristics
1.4.1
Project planning phase
1.4.2
SCM tool selection
1.4.3
Developing strategic objectives
1.4.4
Constructing supply chain structure
1.4.5
Milestone 1: Project outline submission
1.5
Feasibility study
1.5.1
Contract with suppliers and distributors
1.5.2
audit planning
1.5.3
Milestone 2: Completion of design phase
2
Project Execution and closure phase
2.1
Extraction of suitable attributes
2.1.1
Detailing evaluation contents
2.1.2
Screening the unqualified
2.2
Closure phase
2.2.1
Monitoring program
2.2.2
Project monitoring
2.2.3
Milestone 3: Completion of development and implementation phase
2.3
Stakeholders signoff
2.3.1
Final SMC document presentation
2.3.2
feedback analysis
2.4
change management plan
2.4.1
change management implementation
2.4.2
maintenance planning
2.4.3
change management plan implemenation
2.4.4
Milestone4: Final document submission
2.5
training
2.5.1
technical training
2.5.2
non technical training
Figure 2: WBS for the project
(Source: created by author)
Direct labour hourly table
Resource Name
Type
Max. Units
Std. Rate
Base Calendar
Roles
Resource manager
Work
100%
$22.00/hr
Standard
To identify resources
project manager
Work
100%
$35.00/hr
Standard
Tracking and monitoring
Finance manager
Work
100%
$18.00/hr
Standard
Feasibility study
Worker’s tool
Material
$50.00
Meet Project objectives
distributors
Work
100%
$18.00/hr
Standard
suppliers
Work
100%
$25.00/hr
Standard
Supply needful materials
Hardware requirements
Material
$3,000.00
Supply hardware components
Software requirements
Material
$5,500.00
Supply software components
System developer
Work
100%
$35.00/hr
Standard
Develop the system
System tester
Work
100%
$35.00/hr
Standard
To test the system
designer
Work
100%
$22.00/hr
Standard
To design the SCM system
computers
Material
$36,010.00
additional cost
Material
$40,000.00
workers
Work
100%
$35.00/hr
Standard
other cost
Material
$10,500.00
Active precedence table
WBS
Task Name
Duration
Start
Finish
Predecessors
Resource Names
Cost
0
Developing project schedule for SCM
90 days
Tue 11/20/18
Mon 3/25/19
$1,000,000.00
1.0
Project design phase
56 days
Tue 11/20/18
Tue 2/5/19
$555,424.00
1.1
Implementation of project team
12 days
Tue 11/20/18
Wed 12/5/18
$95,344.00
1.1.1
performance analysis
10 days
Tue 11/20/18
Mon 12/3/18
Resource manager,suppliers,Worker’s tool[1],designer,Finance manager,additional cost[1]
$47,010.00
1.1.2
Worker’s skill measurement
2 days
Tue 12/4/18
Wed 12/5/18
3
Resource manager,workers,other cost[1],System developer,computers [1],designer
$48,334.00
1.2
communication management program
23 days
Wed 12/5/18
Fri 1/4/19
$110,368.00
1.2.1
Inventory management plan
12 days
Wed 12/5/18
Thu 12/20/18
4FS-1 day
Finance manager,Software requirements[1],Worker’s tool[1],additional cost[1]
$47,278.00
1.2.2
Team meeting
10 days
Mon 12/24/18
Fri 1/4/19
6FS+1 day,4
additional cost[1],Software requirements[1],System developer,other cost[1],Finance manager,Worker’s tool[1],workers
$63,090.00
1.3
Resource identification
5 days
Mon 1/7/19
Fri 1/11/19
$97,580.00
1.3.1
Gathering
2 days
Fri 1/4/19
Mon 1/7/19
7FS-1 day
project manager,additional cost[1],other cost[1],System developer,Worker’s tool[1]
$51,670.00
1.3.2
Analysis
5 days
Tue 1/8/19
Mon 1/14/19
7FS+1 day
System developer,computers [1],Hardware requirements[1],Software requirements[1]
$45,910.00
1.4
Identification of supply chain characteristics
15 days
Thu 1/10/19
Wed 1/30/19
$165,128.00
1.4.1
Project planning phase
2 days
Fri 1/11/19
Mon 1/14/19
10FF+1 day,9
System tester,project manager,suppliers,additional cost[1]
$41,520.00
1.4.2
SCM tool selection
6 days
Thu 1/10/19
Thu 1/17/19
12SS-1 day
Hardware requirements[1],other cost[1],project manager,workers,Worker’s tool[1],additional cost[1],designer
$57,966.00
1.4.3
Developing strategic objectives
10 days
Wed 1/16/19
Tue 1/29/19
12FS+1 day
System developer,additional cost[1],designer,Hardware requirements[1],Worker’s tool[1]
$47,610.00
1.4.4
Constructing supply chain structure
2 days
Thu 1/31/19
Fri 2/1/19
13FS-1 day,14FS+1 day
Software requirements[1],workers,designer,project manager,System tester,other cost[1]
$18,032.00
1.4.5
Milestone 1: Project outline submission
0 days
Fri 1/11/19
Fri 1/11/19
8
$0.00
1.5
Feasibility study
4 days
Thu 1/31/19
Tue 2/5/19
$87,004.00
1.5.1
Contract with suppliers and distributors
2 days
Tue 1/15/19
Wed 1/16/19
16FS+1 day
project manager,workers,Worker’s tool[1],additional cost[1],System developer,Hardware requirements[1]
$44,730.00
1.5.2
audit planning
2 days
Fri 1/18/19
Mon 1/21/19
18FS+1 day
additional cost[1],designer,project manager,System developer,Resource manager,Worker’s tool[1],suppliers
$42,274.00
1.5.3
Milestone 2: Completion of design phase
0 days
Mon 1/21/19
Mon 1/21/19
19FS-1 day
$0.00
2
Project Execution and monitoring phase
35 days
Tue 2/5/19
Mon 3/25/19
$444,576.00
2.1
Extraction of suitable attributes
11 days
Tue 2/5/19
Tue 2/19/19
$96,880.00
2.1.1
Detailing evaluation contents
6 days
Tue 2/5/19
Tue 2/12/19
22,19SS+1 day
Hardware requirements[1],Software requirements[1],distributors,System developer,Worker’s tool[1],additional cost[1],project manager,designer
$53,830.00
2.1.2
Screening the unqualified
5 days
Wed 2/13/19
Tue 2/19/19
17,23
designer,Finance manager,workers,additional cost[1],Worker’s tool[1]
$43,050.00
2.2
Closure phase
21 days
Thu 2/14/19
Thu 3/14/19
$15,432.00
2.2.1
Monitoring program
2 days
Wed 2/20/19
Thu 2/21/19
24
Resource manager,suppliers,System tester,Worker’s tool[1],other cost[1]
$11,862.00
2.2.2
Project monitoring
5 days
Thu 2/14/19
Wed 2/20/19
26FF-1 day
Finance manager,System developer,Worker’s tool[1],project manager
$3,570.00
2.2.3
Milestone 3: Completion of developmet and implementation phase
0 days
Thu 3/14/19
Thu 3/14/19
34
$0.00
2.3
Stakeholders signoff
6 days
Thu 2/21/19
Thu 2/28/19
$97,874.00
2.3.1
Final SMC document presentation
6 days
Thu 2/21/19
Thu 2/28/19
27
project manager,Finance manager,Software requirements[1],System tester,additional cost[1],Worker’s tool[1]
$49,774.00
2.3.2
feedback analysis
5 days
Thu 2/21/19
Wed 2/27/19
27
designer,suppliers,Finance manager,additional cost[1],Software requirements[1]
$48,100.00
2.4
change management plan
14 days
Thu 2/28/19
Tue 3/19/19
$107,570.00
2.4.1
change management implementation
6 days
Thu 2/28/19
Thu 3/7/19
31,30FF+2 days
additional cost[1],other cost[1],project manager,Software requirements[1],suppliers,System developer,workers
$62,240.00
2.4.2
maintenance planning
5 days
Fri 3/8/19
Thu 3/14/19
33
Hardware requirements[1],System developer,additional cost[1],Worker’s tool[1],designer
$45,330.00
2.4.3
change management plan implemenation
3 days
Fri 3/15/19
Tue 3/19/19
34
$0.00
2.4.4
Milestone4: Final document submission
0 days
Mon 3/18/19
Mon 3/18/19
38
$0.00
2.5
training
13 days
Thu 3/7/19
Mon 3/25/19
$126,820.00
2.5.1
technical training
8 days
Thu 3/7/19
Mon 3/18/19
34SS-1 day
designer,Finance manager,computers [1],suppliers,System tester
$42,410.00
2.5.2
non technical training
5 days
Tue 3/19/19
Mon 3/25/19
38
Resource manager,suppliers,System tester,additional cost[1],computers [1],designer,distributors,Finance manager,project manager,workers
$84,410.00
Activity duration table
WBS
Activity name
Optimistic
Most likely
Pessimistic
PERT estimate
variance
Standard deviation
1.1.1
performance analysis
9
10
12
10.2
1.0
0.50
1.1.2
Worker’s skill measurement
1
2
3
2.0
0.7
0.33
1.2.1
Inventory management plan
10
12
14
12.0
1.3
0.67
1.2.2
Team meeting
8
10
11
9.8
1.0
0.50
1.3.1
Gathering
1
2
4
2.2
1.0
0.50
1.3.2
Analysis
4
5
7
5.2
1.0
0.50
1.4.1
Project planning phase
1
2
4
2.2
1.0
0.50
1.4.2
SCM tool selection
5
6
7
6.0
0.7
0.33
1.4.3
Developing strategic objectives
8
10
11
9.8
1.0
0.50
1.4.4
Constructing supply chain structure
1
2
3
2.0
0.7
0.33
1.5.1
Contract with suppliers and distributors
1
2
4
2.2
1.0
0.50
1.5.2
audit planning
1
2
4
2.2
1.0
0.50
2.1.1
Detailing evaluation contents
5
6
8
6.2
1.0
0.50
2.1.2
Screening the unqualified
3
5
6
4.8
1.0
0.50
2.2.1
Monitoring program
1
2
3
2.0
0.7
0.33
2.2.2
Project monitoring
4
5
7
5.2
1.0
0.50
2.3.1
Final SMC document presentation
5
6
7
6.0
0.7
0.33
2.3.2
feedback analysis
3
5
7
5.0
1.3
0.67
2.4.1
change management implementation
5
6
8
6.2
1.0
0.50
2.4.2
maintenance planning
3
5
6
4.8
1.0
0.50
2.4.3
change management plan implementation
2
3
5
3.2
1.0
0.50
2.5.1
technical training
6
8
9
7.8
1.0
0.50
2.5.2
non technical training
3
5
7
5.0
1.3
0.67
Network Diagram
Figure 3: Network Diagram of the SCM implementation project
(Source: Created by author)
Gantt chart
The Excel Gantt chart designed and developed is given attached excel file.
Resource usage, views, screenshots and tables
Figure 4: Resource over allocation
(Source: Created by author)
Figure 5: After removing resource over allocation
(Source: Created by author)
Tracking Gantt chart view
Figure 4: Tracking Gantt chart view
(Source: Created by author)
Conclusion
From the overall discussion it can be concluded that, the ERP module is performing by the large business organization by a smaller supplier company. The profit structure that can be obtained from the project is also elaborated in this paper. The two sub deliverables followed by the project heads are project design phase and project execution and closure phase. The active precedence table, activity duration table and Excel sheets are being prepared to track the current status of the project.
References
Awang, Z., Hashim, N. N., Yaziz, N. M., & Asmuni, N. S. (2015). Assessing customer intention towards the use of website on online air ticket booking. Editors, 686.
Bowers, J., & Khorakian, A. (2014). Integrating risk management in the innovation project. European Journal of innovation management, 17(1), 25-40.
Calvo-Mora, A., Navarro-García, A., & Periañez-Cristobal, R. (2015). Project to improve knowledge management and key business results through the EFQM excellence model. International Journal of Project Management, 33(8), 1638-1651.
Fernandez-Cavia, J., Rovira, C., Díaz-Luque, P., & Cavaller, V. (2014). Web Quality Index (WQI) for official tourist destination websites. Proposal for an assessment system. Tourism management perspectives, 9, 5-13.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
Ghosal, S., Chaturvedi, S., Taywade, A., & Jaisankar, N. (2015). Android application for ticket booking and ticket checking in suburban railways. Indian Journal of Science and Technology, 8(S2), 171-178.
Larson, E. W., & Gray, C. F. (2014). Project Management: The Managerial Process with MS Project.
Laudon, K. C., & Laudon, J. P. (2016). Management information system. Pearson Education India.
Free Membership to World’s Largest Sample Bank
To View this & another 50000+ free samples. Please put
your valid email id.
Yes, alert me for offers and important updates
Submit
Download Sample Now
Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.
UploadUnique Document
DocumentUnder Evaluation
Get Moneyinto Your Wallet
Total 9 pages
PAY 6 USD TO DOWNLOAD
*The content must not be available online or in our existing Database to qualify as
unique.
Cite This Work
To export a reference to this article please select a referencing stye below:
APA
MLA
Harvard
OSCOLA
Vancouver
My Assignment Help. (2021). Contemporary Leadership Strategies. Retrieved from https://myassignmenthelp.com/free-samples/mgmt6056-contemporary-leadership-strategies/tourism-management-perspectives.html.
“Contemporary Leadership Strategies.” My Assignment Help, 2021, https://myassignmenthelp.com/free-samples/mgmt6056-contemporary-leadership-strategies/tourism-management-perspectives.html.
My Assignment Help (2021) Contemporary Leadership Strategies [Online]. Available from: https://myassignmenthelp.com/free-samples/mgmt6056-contemporary-leadership-strategies/tourism-management-perspectives.html[Accessed 18 December 2021].
My Assignment Help. ‘Contemporary Leadership Strategies’ (My Assignment Help, 2021)
My Assignment Help. Contemporary Leadership Strategies [Internet]. My Assignment Help. 2021 [cited 18 December 2021]. Available from: https://myassignmenthelp.com/free-samples/mgmt6056-contemporary-leadership-strategies/tourism-management-perspectives.html.
×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}
×
Thank you for your interest
The respective sample has been mail to your register email id
×
CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.
Account created successfully!
We have sent login details on your registered email.
User:
Password:
MyAssignmenthelp.com has been providing affordable essay help to thousands of students round the globe. Our essay assistance services can provide solutions and works on essay topics, which are intricate and rare. 200K + students trust us , not without a reason. It is because every assignment and essays have been crafted to precision, edited on various parameters by known essayists and finally proofread and referenced properly to give essays that drive envy
Latest Management Samples
div#loaddata .card img {max-width: 100%;
}
MPM755 Building Success In Commerce
Download :
0 | Pages :
9
Course Code: MPM755
University: Deakin University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers:
Introduction
The process of developing a successful business entity requires a multidimensional analysis of several factors that relate to the internal and external environment in commerce. The areas covered in this current unit are essential in transforming the business perspective regarding the key commerce factors such as ethics, technology, culture, entrepreneurship, leadership, culture, and globalization (Nzelibe, 1996; Barza, 2…
Read
More
SNM660 Evidence Based Practice
Download :
0 | Pages :
8
Course Code: SNM660
University: The University Of Sheffield
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: United Kingdom
Answers:
Critical reflection on the objective, design, methodology and outcome of the research undertaken Assessment-I
Smoking and tobacco addiction is one of the few among the most basic general restorative issues, particularly to developed nations such as the UK. It has been represented that among all risk segments smoking is the fourth driving purpose behind infections and other several ailments like asthma, breathing and problems in the l…
Read
More
Tags:
Australia Maidstone Management Business management with marketing University of New South Wales Masters in Business Administration
BSBHRM513 Manage Workforce Planning
Download :
0 | Pages :
20
Course Code: BSBHRM513
University: Tafe NSW
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Task 1
1.0 Data on staff turnover and demographics
That includes the staffing information of JKL industries for the fiscal year of 2014-15, it can be said that the company is having problems related to employee turnover. For the role of Senior Manager in Sydney, the organization needs 4 managers; however, one manager is exiting. It will make one empty position which might hurt the decision making process. On the other hand, In Brisba…
Read
More
MKT2031 Issues In Small Business And Entrepreneurship
Download :
0 | Pages :
5
Course Code: MKT2031
University: University Of Northampton
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: United Kingdom
Answer:
Entrepreneurial ventures
Entrepreneurship is the capacity and willingness to develop, manage, and put in order operations of any business venture with an intention to make profits despite the risks that may be involved in such venture. Small and large businesses have a vital role to play in the overall performance of the economy. It is, therefore, necessary to consider the difference between entrepreneurial ventures, individual, and c…
Read
More
Tags:
Turkey Istanbul Management University of Employee Masters in Business Administration
MN506 System Management
Download :
0 | Pages :
7
Course Code: MN506
University: Melbourne Institute Of Technology
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
An operating system (OS) is defined as a system software that is installed in the systems for the management of the hardware along with the other software resources. Every computer system and mobile device requires an operating system for functioning and execution of operations. There is a great use of mobile devices such as tablets and Smartphones that has increased. One of the widely used and implemented operating syste…