MBA41 Strategic Project Management

MBA41 Strategic Project Management

Free Samples

MBA41 Strategic Project Management

.cms-body-content table{width:100%!important;} #subhidecontent{ position: relative;
overflow-x: auto;
width: 100%;}

MBA41 Strategic Project Management

0 Download9 Pages / 2,226 Words

Course Code: MBA41
University: Kaplan University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: United States

Question:
You are required to read a case study based on a fictional company and prepare a Statement of Work (SOW) based on the information contained in the case study.The case study will be provided to you in due course.You will be required to include a minimum of 15 references in your Statement of Work at least 5 of which must come from academic journals or textbooks. 
Answer:

This report has depicted the scenario of an arbitrary contractor providing support facilities for the construction company in Australia namely, Pashendale Holdings Ltd (PHL).  PHL had been planning to improve their level of consumers’ service and marketing and this consisted of a multi-tier approach to increasing the market share by acquiring new clientele. In order to achieve, the organization had developed a website redevelopment project, which had been approved by the current CEO of the organization, Virna Pashendale.
Project Scope
            As stated by Mir and Pinnington (2014), project scope defines the deliverables, schedule, milestone, assumptions, constraints and objectives. The key milestones and deliverables in the project are defined by the scope. In this project, a website will be designed for Pashendale Holdings Ltd, which will enable them to enhance the marketing and consumer services.
Project Objectives           
            The purpose of redeveloping the existing website was development of a new website that is rich in content comprising of client testimonials, other industry information, an affiliate network platform, recent company news, and new building developments. However, the organization wished to develop the website having a user-friendly interface for the clients. The website has to be as such that it facilities the company to work more closely to the clientele and provide better solutions.
Project out of scope
            This defines the variables that will lie outside the scope of the study which means that the factors that has been avoided due to shortage of time and budget constraint (Svejvig and Andersen 2015). This project has not included any work that is related to the intranet site of Pashendale Holdings Ltd. This is the reason that the organization will be using contractors having adequate resources for building, designing, implementing and testing the new software. This can be considered as one of the limitation or constraint for the project.
Work Requirements
Project deliverables
            The outcome in the diverse phase of the project that needs to achieved in order to ensure the success of the project is known as the project deliverables (Hornstein 2015).  Project deliverables comprises of both the output and input of each of the phases. The deliverables of the project are as follows:

Task Name

Duration

Start

Finish

New Website Design

74 days

Wed 8/29/18

Mon 12/10/18

1.0 Planning Phase

6 days

Wed 8/29/18

Wed 9/5/18

2.0 website design contractor selection review process

7 days

Thu 9/6/18

Fri 9/14/18

3.0 Execution phase

21 days

Fri 9/21/18

Fri 10/19/18

3.2 Develop testing plan

14 days

Tue 10/2/18

Fri 10/19/18

4.0 Implementation Phase

27 days

Mon 10/22/18

Tue 11/27/18

5.0 Training phase

31 days

Mon 10/22/18

Mon 12/3/18

6.0 Conversion phase

5 days

Tue 12/4/18

Mon 12/10/18

Project Milestone
            As opined by Joslin and Müller (2015), project milestones are tasks having zero duration allotted to them and they signify the progress of the project throughout the overall timeline of the project. The effective execution of the project is dependent on the development of the key milestones. The key milestones facilitates in analyzing the progress report effectively and the key milestones in this project are as follows:

Task Name

Duration

Start

Finish

Milestone 1: Statement of work developed

0 days

Wed 9/5/18

Wed 9/5/18

Milestone 2: Contractor selected

0 days

Fri 9/14/18

Fri 9/14/18

Milestone 4: Website implemented

0 days

Tue 11/27/18

Tue 11/27/18

Milestone 4: training phase completed

0 days

Mon 12/3/18

Mon 12/3/18

Milestone 6: Project completed

0 days

Mon 12/10/18

Mon 12/10/18

Schedule/Milestones
            Todorovi? et al. (2015) states that summary schedule describes all the activities with each of the phases along with the time allotted to each of the task. This means that the project provides the overview of the start and end of each of the activity and the overall outline of the project. In this current project, the project will commence on 29th July, 2018 and will be completed by 10th December, 2018.

Task Name

Duration

Start

Finish

New Website Design

74 days

Wed 8/29/18

Mon 12/10/18

1.0 Planning Phase

6 days

Wed 8/29/18

Wed 9/5/18

1.1 Gather requirements

1 day

Wed 8/29/18

Wed 8/29/18

1.2 Establish metrics

1 day

Wed 8/29/18

Wed 8/29/18

1.3 Develop document of website design

2 days

Thu 8/30/18

Fri 8/31/18

1.4 Sent for approval

1 day

Mon 9/3/18

Mon 9/3/18

1.5 Discuss changes required

1 day

Tue 9/4/18

Tue 9/4/18

1.6 Develop final design

1 day

Wed 9/5/18

Wed 9/5/18

Milestone 1: Statement of work developed

0 days

Wed 9/5/18

Wed 9/5/18

2.0 website design contractor selection review process

7 days

Thu 9/6/18

Fri 9/14/18

2.1 Identify the suitable contractors

2 days

Thu 9/6/18

Fri 9/7/18

2.2 Shortlist suitable contractors

2 days

Mon 9/10/18

Tue 9/11/18

2.3 Choose the most appropriate contractors

3 days

Wed 9/12/18

Fri 9/14/18

2.4 Milestone 2: Contractor selected

0 days

Fri 9/14/18

Fri 9/14/18

3.0 Execution phase

21 days

Fri 9/21/18

Fri 10/19/18

3.1 Website coding

7 days

Fri 9/21/18

Mon 10/1/18

3.2 Develop testing plan

14 days

Tue 10/2/18

Fri 10/19/18

3.2.1 Conduct testing at contractor’s lab

5 days

Tue 10/2/18

Mon 10/8/18

3.2.2 Conduct testing of beta release

5 days

Tue 10/9/18

Mon 10/15/18

3.2.3 resolve coding and site issues

3 days

Tue 10/16/18

Thu 10/18/18

3.2.4 Compile testing report

1 day

Fri 10/19/18

Fri 10/19/18

3.5 Milestone 3: Website design review

0 days

Fri 10/19/18

Fri 10/19/18

4.0 Implementation Phase

27 days

Mon 10/22/18

Tue 11/27/18

4.1 Implement the new website

10 days

Mon 10/22/18

Fri 11/2/18

4.2 Check for issues

10 days

Mon 11/5/18

Fri 11/16/18

4.3 Modify the website

7 days

Mon 11/19/18

Tue 11/27/18

4.4 Milestone 4: Website implemented

0 days

Tue 11/27/18

Tue 11/27/18

5.0 Training phase

31 days

Mon 10/22/18

Mon 12/3/18

5.1 Develop training programs

4 days

Mon 10/22/18

Thu 10/25/18

5.2 Sent for approval

1 day

Fri 10/26/18

Fri 10/26/18

5.3 Train the employees

23 days

Mon 10/29/18

Wed 11/28/18

5.4 Provide weekly update

3 days

Thu 11/29/18

Mon 12/3/18

5.5 Milestone 4: training phase completed

0 days

Mon 12/3/18

Mon 12/3/18

6.0 Conversion phase

5 days

Tue 12/4/18

Mon 12/10/18

6.1 Provide associated documents

2 days

Tue 12/4/18

Wed 12/5/18

6.2 Present project closure report

1 day

Thu 12/6/18

Thu 12/6/18

6.3 Complete project requirement checklist

1 day

Fri 12/7/18

Fri 12/7/18

6.4 Remove 24*7 support

1 day

Mon 12/10/18

Mon 12/10/18

6.5 Milestone 6: Project completed

0 days

Mon 12/10/18

Mon 12/10/18

 

Task Name

New Website Design

   1.0 Planning Phase

      1.1 Gather requirements

      1.2 Establish metrics

      1.3 Develop document of website design

      1.4 Sent for approval

      1.5 Discuss changes required

      1.6 Develop final design

   Milestone 1: Statement of work developed

   2.0 website design contractor selection review process

      2.1 Identify the suitable contractors

      2.2 Shortlist suitable contractors

      2.3 Choose the most appropriate contractors

   2.4 Milestone 2: Contractor selected

   3.0 Execution phase

      3.1 Website coding

      3.2 Develop testing plan

         3.2.1 Conduct testing at contractor’s lab

         3.2.2 Conduct testing of beta release

         3.2.3 resolve coding and site issues

         3.2.4 Compile testing report

   3.5 Milestone 3: Website design review

   4.0 Implementation Phase

      4.1 Implement the new website

      4.2 Check for issues

      4.3 Modify the website

      4.4 Milestone 4: Website implemented

   5.0 Training phase

      5.1 Develop training programs

      5.2 Sent for approval

      5.3 Train the employees

      5.4 Provide weekly update

   5.5 Milestone 4: training phase completed

   6.0 Conversion phase

      6.1 Provide associated documents

      6.2 Present project closure report

      6.3 Complete project requirement checklist

      6.4 Remove 24*7 support

   6.5 Milestone 6: Project completed

 

Task Name

Resource Names

Cost

New Website Design

 

$196,120.00

1.0 Planning Phase

 

$12,600.00

1.1 Gather requirements

System Developer, System Engineer, Testing Engineer

$1,360.00

1.2 Establish metrics

System Developer, System Engineer, Testing Engineer

$1,360.00

1.3 Develop document of website design

System Developer, System Engineer, Testing Engineer

$2,720.00

1.4 Sent for approval

Team manager

$600.00

1.5 Discuss changes required

Advisors ,Chief Marketing Officer, Team manager

$2,600.00

1.6 Develop final design

Advisors ,Chief Marketing Officer, System Developer, System Engineer, Team manager, Testing Engineer

$3,960.00

Milestone 1: Statement of work developed

 

$0.00

2.0 website design contractor selection review process

 

$14,000.00

2.1 Identify the suitable contractors

Advisors ,Chief Marketing Officer

$4,000.00

2.2 Shortlist suitable contractors

Advisors ,Chief Marketing Officer

$4,000.00

2.3 Choose the most appropriate contractors

Advisors ,Chief Marketing Officer

$6,000.00

2.4 Milestone 2: Contractor selected

 

$0.00

3.0 Execution phase

Component cost 1[1]

$92,760.00

3.1 Website coding

System Developer, System Engineer, Testing Engineer

$9,520.00

3.2 Develop testing plan

 

$13,240.00

3.2.1 Conduct testing at contractor’s lab

System Engineer, Testing Engineer

$4,800.00

3.2.2 Conduct testing of beta release

System Engineer, Testing Engineer

$4,800.00

3.2.3 resolve coding and site issues

Testing Engineer

$1,680.00

3.2.4 Compile testing report

System Developer, System Engineer, Team manager, Testing Engineer

$1,960.00

3.5 Milestone 3: Website design review

 

$0.00

4.0 Implementation Phase

Component cost 2[1]

$60,120.00

4.1 Implement the new website

System Developer, System Engineer, Testing Engineer, Team manager, Advisors ,Chief Marketing Officer

$39,600.00

4.2 Check for issues

Testing Engineer, Team manager

$11,600.00

4.3 Modify the website

Testing Engineer

$3,920.00

4.4 Milestone 4: Website implemented

 

$0.00

5.0 Training phase

 

$13,640.00

5.1 Develop training programs

Trainer

$1,760.00

5.2 Sent for approval

Trainer

$440.00

5.3 Train the employees

Trainer

$10,120.00

5.4 Provide weekly update

Trainer

$1,320.00

5.5 Milestone 4: training phase completed

 

$0.00

6.0 Conversion phase

 

$3,000.00

6.1 Provide associated documents

Team manager

$1,200.00

6.2 Present project closure report

Team manager

$600.00

6.3 Complete project requirement checklist

Team manager

$600.00

6.4 Remove 24*7 support

Team manager

$600.00

6.5 Milestone 6: Project completed

 

$0.00

Resource Overview

Name

Cost

Remaining Work

System Developer

$9,200.00

184 hrs

System Engineer

$13,200.00

264 hrs

Testing Engineer

$29,680.00

424 hrs

Chief Marketing Officer

$22,800.00

152 hrs

Advisors

$15,200.00

152 hrs

Trainer

$13,640.00

248 hrs

Team manager

$17,400.00

232 hrs

Project Risk Management

Type of risk

Risk Description

Probability

Impact

Risk reduction Strategy

Contingency Plan

 

 

High

Medium

Low

Performance

Cost

Time

 

 

Internal

Scope creep

yes

 

 

yes

yes

yes

In order to avoid the scope creep, continuous evaluation of the website has to be done so that slight change in the requirement can be identified. The website has to be tested at all phases.

The project manager can make use of the agile methodology instead of using the waterfall methodology, which will increase the flexibility of the project. This will also facilities in making the changes in the requirement at each of the phases of the project.

External

Delay in arrival of hardware and software

 

 

yes

yes

 

yes

In order to reduce this, the contractor has to make sure that they have all the available resources for commencing the project.

The contractors has to keep a buffer time so that even if there is a delay it could be taken into consideration into the time schedule.

Internal

Delay in approval

 

yes

 

yes

 

yes

The project manager will have to develop an effective communication plan so that effective communication between both the parties can be executed at all times.

A moderator wilk have to be assigned for managing and overlooking the meetings.

Acceptance Criteria
            In this current study, the acceptance criteria for the project will be necessary to draw conclusion that both the parties are satisfied and their commitments have been fulfilled. The acceptance criteria from the perspective of Pashendale Holding Ltd are developing the website as per the requirement and providing adequate training to the employees regarding the use of the website. On the contrary, form the perspective of the contractor, the contract should get the specified amount mentioned for the project and the adequate time. The contractor would only develop the website as per the given requirements and additional changes in the requirement later on the project is welcomed only if additional remuneration is being paid for it.
Acceptance
The contractor named below verifies that the terms of this Statement of Work are acceptable. The parties
Here to are each acting with proper authority by their respective companies.

Pashendale Holding Ltd

 

[Contractor company name]

Company name

 

Company name

 

 

 

Full name

 

Full name

 

 

 

Title

 

Title

 

 

 

Signature

 

Signature

 

 

 

Date

 

Date

References and Bibliography
Binder, J., 2016. Global project management: communication, collaboration and management across borders. Routledge.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
Heagney, J., 2016. Fundamentals of project management. Amacom.
H.A., 2015. The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), pp.291-298.
Joslin, R. and Müller, R., 2015. Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), pp.1377-1392.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley & Sons.
Larson, E.W., Gray, C.F., Danlin, U., Honig, B. and Bacarini, D., 2014. Project management: The managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.
Marchewka, J.T., 2014. Information technology project management. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and technology. Routledge.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), pp.278-290.
Todorovi?, M.L., Petrovi?, D.?., Mihi?, M.M., Obradovi?, V.L. and Bushuyev, S.D., 2015. Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), pp.772-783.

Free Membership to World’s Largest Sample Bank

To View this & another 50000+ free samples. Please put
your valid email id.

E-mail

Yes, alert me for offers and important updates

Submit 

Download Sample Now

Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.

UploadUnique Document

DocumentUnder Evaluation

Get Moneyinto Your Wallet

Total 9 pages

PAY 6 USD TO DOWNLOAD

*The content must not be available online or in our existing Database to qualify as
unique.

Cite This Work
To export a reference to this article please select a referencing stye below:

APA
MLA
Harvard
OSCOLA
Vancouver

My Assignment Help. (2021). Strategic Project Management. Retrieved from https://myassignmenthelp.com/free-samples/mba41-strategic-project-management/milestones-and-deliverables.html.

“Strategic Project Management.” My Assignment Help, 2021, https://myassignmenthelp.com/free-samples/mba41-strategic-project-management/milestones-and-deliverables.html.

My Assignment Help (2021) Strategic Project Management [Online]. Available from: https://myassignmenthelp.com/free-samples/mba41-strategic-project-management/milestones-and-deliverables.html[Accessed 18 December 2021].

My Assignment Help. ‘Strategic Project Management’ (My Assignment Help, 2021) accessed 18 December 2021.

My Assignment Help. Strategic Project Management [Internet]. My Assignment Help. 2021 [cited 18 December 2021]. Available from: https://myassignmenthelp.com/free-samples/mba41-strategic-project-management/milestones-and-deliverables.html.

×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}

×

Thank you for your interest
The respective sample has been mail to your register email id

×

CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.

Account created successfully!
We have sent login details on your registered email.

User:

Password:

At MyAssignmenthelp.com, we understand that when students get stuck with tough assignments, they look for affordable services. To assist students with complex assignments, we have built a team of skilled cheap essay writers. MyAssignmenthelp.com has become one stop solution for all students who often look for answers related to their search similar to do my essay at the cheap rate or who can write my essay at affordable prices. Students prefer hiring us as we have the best provisions to render services related to do my essay online at a reasonable rate.

Latest Management Samples

div#loaddata .card img {max-width: 100%;
}

MPM755 Building Success In Commerce
Download :
0 | Pages :
9

Course Code: MPM755
University: Deakin University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answers:
Introduction
The process of developing a successful business entity requires a multidimensional analysis of several factors that relate to the internal and external environment in commerce. The areas covered in this current unit are essential in transforming the business perspective regarding the key commerce factors such as ethics, technology, culture, entrepreneurship, leadership, culture, and globalization (Nzelibe, 1996; Barza, 2…
Read
More

SNM660 Evidence Based Practice
Download :
0 | Pages :
8

Course Code: SNM660
University: The University Of Sheffield

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: United Kingdom

Answers:
Critical reflection on the objective, design, methodology and outcome of the research undertaken Assessment-I
Smoking and tobacco addiction is one of the few among the most basic general restorative issues, particularly to developed nations such as the UK. It has been represented that among all risk segments smoking is the fourth driving purpose behind infections and other several ailments like asthma, breathing and problems in the l…
Read
More
Tags:
Australia Maidstone Management Business management with marketing University of New South Wales Masters in Business Administration 

BSBHRM513 Manage Workforce Planning
Download :
0 | Pages :
20

Course Code: BSBHRM513
University: Tafe NSW

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Task 1
1.0 Data on staff turnover and demographics
That includes the staffing information of JKL industries for the fiscal year of 2014-15, it can be said that the company is having problems related to employee turnover. For the role of Senior Manager in Sydney, the organization needs 4 managers; however, one manager is exiting. It will make one empty position which might hurt the decision making process. On the other hand, In Brisba…
Read
More

MKT2031 Issues In Small Business And Entrepreneurship
Download :
0 | Pages :
5

Course Code: MKT2031
University: University Of Northampton

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: United Kingdom

Answer:
Entrepreneurial ventures
Entrepreneurship is the capacity and willingness to develop, manage, and put in order operations of any business venture with an intention to make profits despite the risks that may be involved in such venture. Small and large businesses have a vital role to play in the overall performance of the economy. It is, therefore, necessary to consider the difference between entrepreneurial ventures, individual, and c…
Read
More
Tags:
Turkey Istanbul Management University of Employee Masters in Business Administration 

MN506 System Management
Download :
0 | Pages :
7

Course Code: MN506
University: Melbourne Institute Of Technology

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Introduction
An operating system (OS) is defined as a system software that is installed in the systems for the management of the hardware along with the other software resources. Every computer system and mobile device requires an operating system for functioning and execution of operations. There is a great use of mobile devices such as tablets and Smartphones that has increased. One of the widely used and implemented operating syste…
Read
More
Tags:
Australia Cheltenham Computer Science Litigation and Dispute Management University of New South Wales Information Technology 

Next

Our Essay Writing Service Features

Qualified Writers
Looming deadline? Get your paper done in 6 hours or less. Message via chat and we'll get onto it.
Anonymity
We care about the privacy of our clients and will never share your personal information with any third parties or persons.
Free Turnitin Report
A plagiarism report from Turnitin can be attached to your order to ensure your paper's originality.
Safe Payments
The further the deadline or the more pages you order, the lower the price! Affordability is in our DNA.
No Hidden Charges
We offer the lowest prices per page in the industry, with an average of $7 per page
24/7/365 Support
You can contact us any time of day and night with any questions; we'll always be happy to help you out.
$15.99 Plagiarism report
$15.99 Plagiarism report
$15.99 Plagiarism report
$15.99 Plagiarism report
$3.99 Outline
$21.99 Unlimited Revisions
Get all these features for $65.77 FREE
Do My Paper

Frequently Asked Questions About Our Essay Writing Service

Academic Paper Writing Service

Our essay writers will gladly help you with:

Essay
Business Plan
Presentation or Speech
Admission Essay
Case Study
Reflective Writing
Annotated Bibliography
Creative Writing
Report
Term Paper
Article Review
Critical Thinking / Review
Research Paper
Thesis / Dissertation
Book / Movie Review
Book Reviews
Literature Review
Research Proposal
Editing and proofreading
Other
Find Your Writer

Latest Feedback From Our Customers

Customer ID:  # 678224
Research Paper
Highly knowledgeable expert, reasonable price. Great at explaining hard concerts!
Writer: Raymond B.
08/10/2021
Customer ID: # 619634
Essay (any type)
Helped me with bear and bull markets right before my exam! Fast teacher. Would work with Grace again.
Writer: Lilian G.
08/10/2021
Customer ID: # 519731
Research Paper
If you are scanning reviews trying to find a great tutoring service, then scan no more. This service elite!
Writer: Grace P.
08/10/2021
Customer ID: #499222
Essay (any type)
This writer is great, finished very fast and the essay was perfect. Writer goes out of her way to meet your assignment needs!
Writer: Amanda B.
08/10/2021
Place an Order

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
×

Powered by essayworldwide.com

× WhatsApp Us